School board gets
update on construction By PAT NEWMAN
Staff Writer
The
Fayette County Board of Education was updated on
about 30 ongoing school construction projects
Monday night during a sparsely attended regular
meeting.
Mike
Satterfield, projects director for the school
system, reported that site grading for the
Starr's Mill High School stadium is about 95
percent complete. He asked the board to approve a
change order, adding $30,000 to the overall cost
of the $2.1 million stadium, for irrigation and
sod. He explained that the job could not be done
any cheaper.
Although,
this was the first addition to the contract,
superintendent Dr. John DeCotis assured the board
that future deductions anticipated in the project
would balance it out. Timely installation of the
sod should provide a grassy soccer field for
spring, Satterfield noted.
The
concrete slab foundations have been poured for
the Flat Rock Middle School auditorium and the
steel frame structure is completed. Masonry work
has begun. At North Fayette Elementary, kitchen
demolition has begun in preparation for a new
kitchen facility.
Progress
on special projects include:
” Grading work complete at the
McIntosh High School fields with an irrigation
system and sod installed
” Fencing has been installed
and an infield has been dug at Starr's Mill High
School's softball field. Dug-outs are under
construction.
” Grading has been completed
at the Starr's Mill High School practice field
with installation of an irrigation system 95
percent complete. The field is being prepared for
sod.
” Rough grading and
installation of fencing has begun on the Starr's
Mill High School baseball field.
” The retainer wall has been
installed and ground leveled for landscaping at
the Rising Starr game field.
” Work is 75 percent complete
on reroofing of building A at the Lafayette
Educational Center.
|